New construction / Rehabilitation
Client
Hospices Civils de Lyon
Construction cost
€ 111,9 Million excluding tax
Net Floor Area
30 200 m² Total
12 600 m² New Area
16 200 m² Rehabilitation
1 400 m² Temporary
Date
2020 - 2027
Phase 1: Handover of the Emergency Department in March 2024
PROGRAM
Operating blocks (30 rooms)
45 beds, including 30 intensive care beds and 15 continuous care beds
Trauma centre
Emergency reception service
Automated logistics
TEAM :
Architect
MICHEL RÉMON & ASSOCIATES
Project Manager Michel Rémon & Associés
MARIE-CLAUDE RICHARD
STEVE BALME
Associate architect
VK architects
Landscape - urban planner
Atelier AS Marguerit
Engineering & Economist
OTE Ingénierie
Cost consultant
GBA & Co
Biomed equipment and hospital advice
Icade Promotion
Hospital logistics advice
Prologue
Sustainability
Otelio
Asbestos Removal
Antea Group
Signage
Ariane signalétique